Two Mile Creek Erosion Protection
Creek bank protection works to prevent creek bank erosion and erosion of properties which has been an ongoing issue. This project began in June 2023 and will take approximately one year to finish.
For detailed information on this project visit westernbay.govt.nz/two-mile-creek
Date: 2024
Two Mile Creek Erosion Protection - Extension
Read more about this project on our dedicated Two Mile Creek Stream Protection page.
Category 1 Projects
Projects Council has committed to complete by July 2024.
Project Name | Description | Update |
Two Mile Creek Erosion Protection | Rock revetment of Two Mile Creek to protect properties from erosion. | Physical works underway and progressing well. |
Floodgate Wilson Road Culvert | Investigate the benefit of Installing a flap gate at 53 Wilson Road. | Modelling complete. Flood gate to be installed at Wilson Road culvert. |
Category 2 Projects
Projects Council has committed to progressing to detailed design.
Project Name | Description | Update |
25 Wilson Road Improvements | Carpark extension and sealing linked to concrete dish channel capacity. | Carpark extension is complete. Further work to be done on installing the dish channel. |
The Crescent Rd Runoff Management | Investigate existing network capacity constraints, look at the effects of privately owned soakage network in the area on overland flow causing downstream flooding, investigate the use of mega or super pits in steep sections of The Crescent, investigate use of Wilson Park for attenuation, investigate connecting The Crescent properties to Wilson Park. | Design is complete and under review. |
Category 3 Projects
Projects Council are considering for this catchment. A consultant has been engaged to undertake modelling for the following projects.
Project Name | Description | Update |
Improvement of Flowpath through Coronation Park | Assess options to improve flow through open swale. | Project was modelled and found to have no stormwater benefit so will not be progressed further. |
Two Mile Creek Upper Catchment Attenuation | Upper catchment attenuation to support diversion of Maranui Estate to Two Mile Creek. | Stormwater modelling complete. Options under review. |
Otto Road SW PS/Reticulation | Assess the feasibility of installing a pump to mitigate flooding. | Stormwater modelling complete. Options under review. |
Shaw Road Pump | Could direct some of the water down to Two Mile Creek below Dillon Street bridge. | Stormwater modelling complete. Options under review. |