Catchment Projects: Ōtawhiwhi, Bowentown, Pio Shores
Category 1 Projects
Projects Council has committed to complete by July 2024.
Project Name | Description | Update |
Basins Maintenance | Soakage basins require scouring to break up firm sand which inhibits soakage in the dunes at Bowentown. | The basins have now been scoured to ensure water can drain through the dunes. |
Clearance Regrading of Bowentown Open Drain Network | Improve flows through to Otāwhiwhi drain. | Improvement to the open drains will be undertaken in conjunction with the upgrade to the Otawhiwhi drain and wider Pio Shores work. |
Category 2 Projects
Projects Council has committed to progressing to detailed design.
Project Name | Description | Update |
Otāwhiwhi Drain | Initial concept of a box culvert extending into the harbour with some other erosion protection and stormwater treatment, will help hapu reclaim some land and improve flow and water quality. | Initial meeting with Marae complete. Concept design is now complete and with Marae for feedback. |
On Call Pumps with Dedicated Wet Wells to Protect Properties from Flooding | Install dedicated manholes to provide a dedicated location for portable pumps to be dropped in during extreme weather events. Portable pumps will pump flood waters over to permanent pump station. | Concept design has been undertaken, review underway. |